You love the street, the school zone and the block. The house is the problem. A knockdown rebuild keeps the location and replaces the home, and in Perth’s established suburbs a rebuild is often the better choice over a large renovation.

This guide covers each step, the costs owners miss, and a realistic timeline, from a builder who does this work in Bicton, Attadale and Applecross.

Custom home built by Skytree Homes in Bicton, Western Australia (2024)

Knockdown Rebuild or Renovate?

A renovation makes sense when the structure is sound and you want to change one or two areas. A knockdown rebuild makes more sense when:

  • The house needs new wiring, plumbing and roofing at the same time
  • The floor plan works against the way you live
  • You want a second storey and the existing footings will not carry one
  • Renovation quotes come close to the cost of a new home

Older homes also hide surprises behind the walls. Asbestos, termite damage and failed footings add cost to a renovation mid-job. With a rebuild, those risks sit at the start, before your new home is designed.

Steps 1 and 2: Check the Block, Then Design

Before design, confirm what the site allows. Your local council sets the zoning and R-Code density, which control setbacks, site cover and height. Some streets carry heritage or character controls. A feature survey and a soil test show the levels, existing services and footing needs.

A new home on an established lot works around the neighbours, mature trees, the slope and the sun. A narrow lot pushes living space up. A wide lot allows a single-level plan with a large alfresco. Design and documentation usually take 3 to 6 months, including engineering.

Custom home built by Skytree Homes in Karnup, Western Australia (2025)
Custom home built by Skytree Homes in Bicton, Western Australia (2024)

Step 3: Approvals

Demolition comes first. Your local council issues a demolition permit for the existing house, and planning approval is needed if the design departs from the R-Codes or sits in a heritage area.

Once all documentation is ready, costings are finalised and the building contract is signed, the following building approvals are processed:

  • BA3: Certificate of Design Compliance (CDC). A certified building surveyor reviews all documentation and specifications and certifies that the design complies with Western Australian standards and the National Construction Code. It is lodged with the Building Permit application.
  • BA4: Building Permit. The official approval issued in WA that grants legal permission to begin construction.
  • BA20/BA20A: Encroachment and Adverse Effects / Protection, Access and Shared Structures. Required when the new home crosses the neighbour’s boundary or could affect neighbouring structural stability, bearing capacity or site drainage. BA20A is a notice and request for consent for neighbour arrangements, such as protection structures beyond the boundary or removing or replacing fences for access.

Before work starts, a registered builder also takes out home indemnity insurance and pays the Construction Training Fund levy where it applies.

Steps 4 and 5: Demolish, Then Build

Water, power, gas and NBN all need formal disconnection before demolition. Each provider runs its own process, so book early. Bonded asbestos over 10 square metres must go out with a licensed removalist, and many homes built before 1990 contain some. Demolition itself takes days, but disconnections and asbestos removal add weeks.

Construction runs through site works, slab, frame, roof, lock-up, fit-out and handover. Construction averages 1 year from Building Permit approval, depending on the build complexity. Our Karnup home took 8 months.

Custom home built by Skytree Homes in Karnup, Western Australia (2025)
Custom home built by Skytree Homes in Bicton, Western Australia (2024)

Costs Owners Miss

The build price is only part of the budget. Allow for:

  • Demolition and asbestos removal
  • Service disconnections and new connections
  • Site works on sloping or sandy blocks, including retaining
  • Council fees, permit fees and levies
  • Rent or a second mortgage while you live elsewhere for 12 months or more
  • Landscaping, fencing and driveways, often outside the build contract

Our guide to the cost to build a house in Perth covers site, size and specification in more detail.

How Long Does a Knockdown Rebuild Take?

Design comes first and takes 3 to 6 months. After that, the timeline runs in this order:

  • Approvals: demolition permit, then BA3, BA4 and BA20/BA20A where needed
  • Disconnections and demolition: 3 to 6 weeks
  • Construction: average 1 year from Building Permit approval, depending on the build complexity

Weather, trade availability and supply delays can all move a program. Projects that start in winter are more prone to weather delays, so we plan around them early.

See our full Perth build timeline and the real build times of our recent homes.

Case Study: Building in Bicton

Bicton sits in the City of Melville between Attadale and East Fremantle, and almost every project there starts with an existing home on a generous block. That means demolition, service disconnections, mature trees and neighbours on both boundaries are part of the job from day one.

Our Bicton custom home with pool was built over 9 months: a timber-framed home with polished concrete floors and a large pool planned at slab stage. Our second Bicton project followed the same approach, with the early site work planned as carefully as the design. Read more on our home builders in Bicton page.

Custom home built by Skytree Homes in Karnup, Western Australia (2025)

Knockdown Rebuild Perth: Frequently Asked Questions

Do I need a demolition permit in Perth?
Yes. Demolition of a house needs a permit from your local council before work starts.
Do I need to move out?
Yes. Plan for 12 months or more away from the property during demolition and construction.
Does one builder handle demolition and the new home?
We manage demolition, disconnections and construction under one contract, so you deal with one team.
Is a knockdown rebuild cheaper than renovating?
For a full renovation of an older home, the costs often land close together, and a new build gives you a new structure, new services and a design built around your life.

Planning a knockdown rebuild?

We build a small number of homes at a time across Perth’s river suburbs. See our Bicton knockdown rebuild work, our completed projects, or call to talk through your block.